JIC Recovery Release No. 34 - GPA Update; GRTA Shuttle Service
GPA Update:
The Guam Power Authority (GPA) continues its restoration and post-typhoon recovery efforts. GPA reports that as of 1:00 p.m.:
-
53.2% of the System Load (Customer Demand) has been restored.
-
95.8% of GPA’s Substation Energization has been restored.
-
88.9% of GPA’s feeders/circuits have been energized/restored.
Two additional feeders/circuits were added to the island-wide system for a total of 56 feeders/circuits that are partially energized today.